Ontario Construction Secretariat releases its fourth Coronavirus Contractor Survey

The Coronavirus Contractors Survey 4: Stability & Anxiety is released as the fourth survey in a series of independent studies conducted by the Ontario Construction Secretariat (OCS).

Between September 8 and 18, 2020, the OCS led a Contractor’s Survey of 300 ICI (Industrial, Commercial, and Institutional) contractors on how the construction industry is showing signs of stability but anxiety over a second wave of COVID-19.

The survey has found that the threat of a second wave of COVID-19 is the biggest concern of contractors. There has been little change over top concerns from previous surveys including supply chain disruptions, skilled labour availability, and ensuring the health and safety of workers and staff. However, there has been a significant decline in concern regarding project cost over-run due to sanitization, safety, and social distancing protocols.

Contractors report that on average, 23 per cent of their work has stopped because of the coronavirus, down from 28 per cent in Survey 3 and they testify that 29 per cent of work is delayed, down from 41per cent in Survey 3. Up from the previous survey, 56 per cent of contractors say most or all of their work has now resumed.

The financial impacts of the pandemic remain significant to the industry as 54 per cent of contractors said their business was growing before the pandemic and now only 13 per cent report growth. Pre pandemic, merely 3 per cent said their business was in decline whereas 33 per cent report a current drop.

According to the survey, 66 per cent of firms expect less revenue in 2020 compared to 2019 — an improvement from earlier surveys where close to three-quarters of contractors anticipated lower revenues. The magnitude of revenue loss also continues to improve with contractors now expecting an average of 16 per cent decline.

Supply chain disruptions have not improved since the pandemic began in March, with 64 per cent reporting high or medium impacts on business. Building permit processing has been reported lower than pre-pandemic by 52 per cent of contractors, and 46 per cent had difficulty getting skilled labour.

Projections for the remainder of 2020 reveal 51 per cent of contractors expect to do less work in the September – December period compared to last year where 19 per cent of contractors expected more work. Approximately 37 per cent of contractors expect it to be more difficult to obtain skilled labour compared to September – December 2019, while 10 per cent expected it to be less difficult.